Transfer Station
May 20, 2025
The generator and propane tank are set in place at the transfer station. Travis is going to try to have them hook up by May 30. (depending on weather conditions)
Town Hall
May 01, 2025
Due to tornado damage the Town Hall will be getting a new roof and new siding. Also having 1 wall repaired. The Town is currently seeking bids for work to be done. The quotes will be discussed at the May 12th meeting.
Update on transfer station
May 01, 2025
Update: The project for the generator and propane tank to be placed at the transfer station is set to be completed by the end of July 2025.
Park sign
March 03, 2025
The city park sign located on Roasting Ear Rd. Is currently being redone. Thank you Richard & Dove Wible
Transfer station
February 11, 2025
Forgiveness funds for the generator and propane tank to be installed at the transfer station have been approved. The project must be completed by the end of the year or funds will be added to the loan.
The easement for the property at the transfer station has been filed at the court house.
Baseball field
December 03, 2024
The baseball field at the town park is expected to be completed by spring of 2025.
Town of Fifty Six has a Brand New Website! Subscribe to Stay Informed!
July 30, 2024
Working harder to better serve and communicate with our community, we have launched a new website for our water customers. Check it out and let us know what you think. Subscribe today!